Plan Review Requirements

New construction or renovations to an existing building will require a plan review prior to beginning construction.

Alabama law 34-2-32 requires plans and specifications to be prepared by a registered architect for all buildings that are 2,500 square feet or more.

The Plan Review Application and documents should be submitted to [email protected] at the Bureau of Environmental Services, Manufactured Food Processing Program for review.

Hard copies of the Plan Review Application, drawings/plans, and documents can be mailed to:

Bureau of Environmental Services
ATTN: Manufactured Food Processing Branch
201 Monroe Street, Suite 1250
Montgomery, AL 36104

Facility Design Guidance

Good Manufacturing Practices (GMPs) provide insight on how to design a facility centered on food safety. A well planned flow of food through the facility helps maintain its safety. Thinking of your processes and how foods will be handled allows you to design a building that works for you.

The guidance below mirrors GMPs and details the information necessary to complete a plan review. For more details about plan review requirements, see Chapter 420-3-20.08 in the Administrative Code Chapter 420-3-20 Food Processing Establishment Sanitation.

Grounds

  • Site plans that show the location of the building on the property, dumpsters/trash, receiving, and shipping loading docks, water source, sewage disposal
Construction & Design
  • Sized adequate for the operation and volume of production anticipated
  • Process Flow considered in the layout of the interior of the facility and equipment
  • Floor plans drawn to scale, to include:
    • Receiving
    • Storage (raw materials, finished products, and containers)
    • Production Lines and Equipment
    • Handwashing Sinks
    • Warewashing Area (if applicable)
    • Quality Assurance Lab (if applicable)
    • Employee Breakroom
    • Restrooms
    • Shipping
    • Finish schedule of materials used for floors, walls, cove base, and ceilings
    • Construction details showing elevation drawings, onsite built equipment, and cabinetry
    • Door schedule identifying door closures, hardware, and pest protection
    • Equipment schedule labeling each piece of equipment
    • Mechanical plans to include air conditioning & heating units, vent locations, fan installation locations, and restroom recirculating fans
    • Lighting plans showing locations of light fixtures, indicate light intensity, and shielding
    • Plumbing plans indicating the location of wastewater lines, freshwater lines, grease trap (if applicable), water heater, fixtures, drain design (direct or indirect), floor sinks, and floor drains
Additional Documentation
  • Equipment specification sheets for each item installed showing the dimensions, make, and model number.
    • Customized equipment should be included in the plan’s construction details.
    • Food contact surfaces must be corrosive-resistant, non-toxic, designed for easy cleaning, and able to withstand its intended use.
    • Specification sheets for thermometers, pH meters, and water activity meters should be included.
  • Food Safety Plan
    • Identify Hazards
    • Process Controls or Critical Control Points (CCP’s)
  • Standard Operating Procedures (SOP’s) addressing these following items:
    • Personnel
    • Employee Sick Policy
    • Hygienic Practices
    • Education and Training
    • Flow of Food
    • Source
    • Receiving
    • Storage
    • Preparation
    • Cooking
    • Cooling
    • Packaging
    • Sampling
    • Storage
    • Transport & Distribution
    • Allergen Cross-Contact
    • Cleaning and Sanitizing
    • Pest Control
    • Sanitary Processes and Controls
    • Warehousing and Distribution
    • Supply Chain
    • Recall Process
    • Reportable Food Registry (RFR)
  • Labels and Packaging for Each Item Manufactured
  • Distribution Plan
  • Special Processes Documentation (if applicable)

 

Next: Permitting